ABOUT THE PROJECT
This city's sewer main infrastructure along 1200 South from US-89 to Main Street(SR-165) will need to be upsized for greater capacity. As such, necessary improvements are essential to maintain a reliable sewer system for properties adjacent to the work and community expansion.
Construction is anticipated to begin on June 22, 2026 and will start on the far west side of the project area (see project map). Traffic control and local road closures will vary depending on active work zones to maintain safety for the public and crews. Local access for businesses will be briefly restricted but otherwise maintained. Appropriate business access signage will be provided by contractor when necessary.
CONSTRUCTION SCHEDULE

---------------------------------------------
Project Start: June 22, 2026
Days: Monday-Friday
Hours: Mostly Daylight hours; occasional nighttime work possible
Approx. Project Completion: September 15, 2026
Schedule is subject to change due to weather and materials available

Traffic Control Plan
Traffic Plan Details TBA as work approaches
-
Work locations will be broken out into three phases (See Flyer)
-
Traffic will be detoured accordingly depending on active work areas.
-
Shoulder parking will be restricted inside construction zones.
-
Brief property access restrictions may occur as work progresses. Crews will provide signs to indicate business access points and detours.
Drivers should slow down and use caution!
*The dedicated Public Involvement Team will provide pictures of the project site here upon acquisition